Panorama City Skilled Nursing Center

Location: 
Lacey, Washington
Size: 
92,500 SF
A&P Role: 
CMGC/CMAR

The Panorama Convalescent and Rehabilitation Center project involved the demolition of a single-story facility and construction of a two-story, 92,500-square-foot skilled nursing facility with 155 licensed beds. The new building was completed in two phases, allowing residents to move into Phase I while the original facility was demolished and Phase II was built.  For this project the team utilized a cost-effective steel framing panel system that is environmentally sustainable, energy efficient and non-combustible, and also saves time in construction. The panels were fabricated off site with just-in-time delivery, allowing the project to be completed three months early.